Sun Microsystems, Phases II and III

Sun Microsystems, Phases II and III

On a large, 19 hectare site close to Junction 4a of the M3 motorway near Camberley, IT giant Sun Microsystems is in the process of establishing a major office and laboratory complex. And HBG Construction is busy working on the second and third of the three-phase project, having completed Phase I in September 2000.

In all, the £70 million Guillemont Park Development involves the construction of five buildings, a large 1,800-plus space car parking area, access infrastructure, and extensive landscaping, including lakes, swales and other water features. In Phase I, HBG Construction has built two substantial buildings - Java House and Solaris House - featuring offices, computer suites, recreational and dining facilities – all linked by a network of internal communication 'streets'. This, together with most of the car parking, roadway works and landscaping, was completed in September.